Saturday, October 30, 2010

4th Day Bricking


They are still working on installing brick for this house today.

Friday, October 29, 2010

Third Day Bricking


It is third day they spent on install brick.

Wednesday, October 27, 2010

Start to Install Brick


Today, the installation of brick is started.

Monday, October 25, 2010

Brick is Here!


It is ready to install the brick for this house. It is part of step 6 out of total 12 steps.

Wednesday, October 20, 2010

Roof Installed


The roof is finished for this new house last night.

Tuesday, October 19, 2010

Roof



Today, they are working on roof for this house. It is step 4 to build the house.

Friday, October 15, 2010

Windows Installed



They started to install windows today.

Thursday, October 14, 2010

Outside Night View



Night view of this house at this stage. Today, workers worked on putting board around the house.

Fouth Day Framing



The framing is about finished for this new house.

Tuesday, October 12, 2010

Framing Third Day



After 3 days framing, it is what it looks like today.

Sunday, October 10, 2010

Second Day Framing



This is the result of second day framing.

Friday, October 8, 2010

Framing Starting



This morning, they started the framing of this house. Normally, it takes 3 to 4 days to finish up it.

Thursday, October 7, 2010

Material is here



Since the foundation is finished, they ship the material for this house today. It is in the step 2 to build it.

12 Steps to Build This House



Based on the builder, there are 12 steps after finishing design.

Step 1, Prepare lot, Plumbing
Step 2, Foundation and Frame
Step 3, Roof Rafters
Step 4, Roof, Window, Plumbing
Step 5, Gas and Electric
Step 6, Insulation, Brick, Drive Way Concrete
Step 7, Paint, Cabinet, Doors
Step 8, Paint Wall, Tile Bath
Step 9, Eclectic, Fence, Mirror
Step 10, Tile, Grass, Lock
Step 11, Electricity and Gas Meter, Carpet
Step 12, Closing

Wednesday, October 6, 2010

Foundation Installed



Today, they came to install the foundation for this new house.