Monday, December 20, 2010

Installing Fence


Today, they came to dig holes for installing fence.

Tuesday, December 14, 2010

Fireplace Done


It is in step 8 out of total 12 steps.

Thursday, December 9, 2010

Inside Painted


The inside of this house is painted.

Saturday, December 4, 2010

Cabinet and Wood Floor Installed


These two days, worker came and installed cabinet and wood floor for this house.

Saturday, November 27, 2010

Garage Door Installed


Today, the garage door is installed for this new house.

Monday, November 22, 2010

Concrete for Patio


Today, they get drive way and patio done. Step 6 is finished.

Sunday, November 21, 2010

Drive Way


It is ready to get drive way for this house.

Thursday, November 18, 2010

Paint Outside


Today, worker came and paint outside for this house.

Tuesday, November 16, 2010

Insulation Installed


Insulation is done for this new house. Now, it is in step 6 out of total 12 steps.

Sunday, November 14, 2010

Fireplace Installed


Fireplace is installed for this house.

Monday, November 8, 2010

Brick Installation Finished


Finally, it is finished from outside.

Wednesday, November 3, 2010

Electicity Wire Installed


Electricity wires are installed for this house.

Tuesday, November 2, 2010

Still Working on Bricks


They are still working on installing bricks for this house. Normally, it will not take this long. Since it is a spec home, they are trying to make it pretty for quick sell.

Saturday, October 30, 2010

4th Day Bricking


They are still working on installing brick for this house today.

Friday, October 29, 2010

Third Day Bricking


It is third day they spent on install brick.

Wednesday, October 27, 2010

Start to Install Brick


Today, the installation of brick is started.

Monday, October 25, 2010

Brick is Here!


It is ready to install the brick for this house. It is part of step 6 out of total 12 steps.

Wednesday, October 20, 2010

Roof Installed


The roof is finished for this new house last night.

Tuesday, October 19, 2010

Roof



Today, they are working on roof for this house. It is step 4 to build the house.

Friday, October 15, 2010

Windows Installed



They started to install windows today.

Thursday, October 14, 2010

Outside Night View



Night view of this house at this stage. Today, workers worked on putting board around the house.

Fouth Day Framing



The framing is about finished for this new house.

Tuesday, October 12, 2010

Framing Third Day



After 3 days framing, it is what it looks like today.

Sunday, October 10, 2010

Second Day Framing



This is the result of second day framing.

Friday, October 8, 2010

Framing Starting



This morning, they started the framing of this house. Normally, it takes 3 to 4 days to finish up it.

Thursday, October 7, 2010

Material is here



Since the foundation is finished, they ship the material for this house today. It is in the step 2 to build it.

12 Steps to Build This House



Based on the builder, there are 12 steps after finishing design.

Step 1, Prepare lot, Plumbing
Step 2, Foundation and Frame
Step 3, Roof Rafters
Step 4, Roof, Window, Plumbing
Step 5, Gas and Electric
Step 6, Insulation, Brick, Drive Way Concrete
Step 7, Paint, Cabinet, Doors
Step 8, Paint Wall, Tile Bath
Step 9, Eclectic, Fence, Mirror
Step 10, Tile, Grass, Lock
Step 11, Electricity and Gas Meter, Carpet
Step 12, Closing

Wednesday, October 6, 2010

Foundation Installed



Today, they came to install the foundation for this new house.

Thursday, September 30, 2010

Cable Installed


Cable is installed for this new house.

Sunday, September 26, 2010

Ready for Cable


Cable is here and ready to be installed this coming week.

Pipe



Last week, the pipe was there for this new house.

Saturday, September 4, 2010

Digging



There are total 12 steps to build a house in this community. Yesterday, they started digging for this new house. It is in step 1.

Monday, August 30, 2010

Preparing for Foundation 1




Today, workers came and lay out this with board. It take about one hour.

Saturday, August 28, 2010

New House Coming



Yesterday, this lot got cleaned and leveled for a new house.

Friday, February 5, 2010

Today House Closed


Today, it is closing day. The family got this house today. We are looking foward to meeting them soon.




Friday, January 22, 2010

Almost Finished and Ready to Close

Now, workers come to have a final touch up and ready for close next week. It is in final step out of 12 of them.

Tuesday, January 19, 2010

Carpet Installed Today

Today, workers came and installed the carpet for this new house. Now, it is in 11 step out of 12 steps.

Wednesday, January 13, 2010

Wood Floor Painted


Today, they finished the painting this wood floor. It looks great! It is hardwood foor with nail down.

Tuesday, January 12, 2010

Wood Floor Finishing Up


Now, workers are finishing up the wood floor for this new house and get it ready for painting.

Monday, January 11, 2010

Garage Door Painted


The garage door is painted.

Friday, January 8, 2010

Stove Installed


Stove is installed for this new house. And heater is on to make this house warm. Both of them are using gas.

Thursday, January 7, 2010

Sprinkle System Installed

Here is the controller of this system.

Tuesday, January 5, 2010

Microwave Oven Installed


Microwave and Oven are installed for this new house. Electricity is turned on.

Monday, January 4, 2010

Lawn Installed

Today, the lawn is installed for this new house. It is in step 10 out of 12 steps.