have the meeting with the house owner next Monday. That will be the final floor plan go through meeting. After that, nothing can be changed theoretically.Wednesday, April 29, 2009
Dig for Foundation
Today, worker came to dig channels for laying out foundation. The builder told me that he will
have the meeting with the house owner next Monday. That will be the final floor plan go through meeting. After that, nothing can be changed theoretically.
have the meeting with the house owner next Monday. That will be the final floor plan go through meeting. After that, nothing can be changed theoretically.Tuesday, April 28, 2009
The Lot
Electricity Pole
Friday, April 24, 2009
Mark the land
Today, three groups of people came and work on this lot. First group, two workers came to measure the land and mark the land. Second group of 7 people got here put stacks on the four corner of the land and and lay out the outline of the foundation with board. Third group, one man arrived with several tools and found the electricity line, gas line and phone lines; and mark the lines with red paint and yellow paint.According to builder, there are 12 steps to finish building one house. Each step takes about 2 weeks.
It will take about 24 weeks to finish it.
It will take about 24 weeks to finish it.From the layout of the board, we can tell the house is neither wide nor long. This house is the last one to be built on this street. It will have the best view since it is at the end of the street. Outside of the community wall, there is a treeline alone a small creek. The land in front of the treeline is a kind of narrow and owned by the city.
Tuesday, April 21, 2009
Start to build a new house