Monday, October 26, 2009

Pipes Installed


Pipes and electricity wires are installed inside this new house.



Thursday, October 22, 2009

Roof Installed

Roof and windows are installed for this new house.

Tuesday, October 20, 2009

Windows installed

Today, workers came to install the windows for this new house. The siding is also installed. They started to work on roof at same time.

Monday, October 19, 2009

Framing is done

Framing is finisshed for this new house. Step 3 will be started soon.

Monday, October 12, 2009

4th Day for Framing

This is 4th day, workers work on framing for this house. The weather is not good but ok.

Thursday, October 8, 2009

Third Day Working on Framing

It is third day they are working on framing for this house. It is a 4500 sqf house.

Wednesday, October 7, 2009

Frame for First Floor

Today, workers came and worked on first floor for this new house.

Tuesday, October 6, 2009

Start Framing

Although there is some rain in last few days, they started framing for this new house today.

Friday, October 2, 2009

Foundation Installed


This morning, workers came to put foundation for this new house.